Stage 1 - Commencement (may be combined with stage 2). Minimum 2 days notice
Stage 2 - Inspection of new excavation for foundations
Stage 3 - Inspection of oversite (can be combined with stage 4)
Stage 4 – Inspection of new walls dpc and below ground drain pipes for falls and line
Stage 5 - Inspection of damp-proof membrane and insulation for new ground floor
Stage 6 - Inspection of wall / roof Insulation and roof and floor structure
Stage 6a - Inspection of steel beams in loft area
Stage 6b -Inspection of floor, wall and roof timbers and insulation
Stage 7 – Inspection of Drainage connections (if any)
Stage 7a - Drain tests of new drains - witnesses of drain tests after backfill
Stage 8 - Completion of work (fire doors, closers, smoke detectors and fire alarms and fire resistance measures, stairs, handrails, room ventilation, headroom and receipt installer certificates received).